Boskalis awarded €111 m Hornsea 2 contract

By Mike Hayes01 May 2019

orsted hornsea 2 wind farm

Impression of the UK’s proposed Hornsea 2 offshore wind farm

Royal Boskalis Westminster has announced it has won a cable installation contract for the UK’s Hornsea 2 offshore wind farm.

The contract, awarded by Ørsted Wind Power and said to be valued at over €111 million, will include the laying of three export cable circuits, with a total length of some 380 km.

The scope of the contract includes the preparation of the cable route – comprising a geophysical survey, the clearance of obstructions and seabed levelling through dredging.

Boskalis will also utilise horizontal directional drilling over a distance of some 300 m, to cross the sea defence of Horseshoe Point in Yorkshire.

The company said it will need to deploy a number of specialist vessels for the project, including a trailing suction hopper dredger and multiple cable-laying vessels. One of its latest construction vessels, capable of pulling a plough able to withstand 200 tonnes of continuous pull, will also be used.

The Hornsea 2 wind farm, located 90 km off the UK coast, will ultimately comprise 165 turbines, with a maximum capacity of 1.4 GW.

Latest News
CM Labs envisages the job site of the future
icher-Lanciault, product manager, CM Labs, shares his thoughts on the job site of the future
Spacecraft supports legendary lifting and moving
One of the most revered jobs over the past 40 years was anything to do with the NASA Space Shuttle.
Gordan named Link-Belt transportation manager
Gerald Gordon brings nearly 20 years of experience in the logistics industry.