Doosan Heavy's deal to upgrade power plant

14 March 2017

South Korean-based Doosan Heavy Industries & Construction has bagged a KRW300 billion (US$262 million) deal to help upgrade the Muara Tawar power plant in Indonesia.

According to the deal made with the Indonesian government-owned corporation Perusahaan Listrik Negara (PLN) – who have a monopoly on electricity distribution in the region – Doosan will work in tandem with a state-run Indonesian construction firm.

As South Korea’s top power equipment maker, Doosan said they have agreed to provide three steam turbines and eight boilers.

Over the next 30 months, the capacity of the gas-powered plant will be increased from the current 1,150MW to 1,800MW.

In December of last year, Doosan also won a similar deal in Indonesia worth KRW180 billion (US$157 million).

Latest News
Jury concludes that Caterpillar owes $100m to importer amid US lawsuit
A jury in the US has concluded that Caterpillar must pay $100 million to an importer, following a legal dispute between the two companies.
Kanamoto eyes North America move
Company aims to double overseas revenue in next six years
Smart Construction to unveil Edge 2 at Intermat
New launch ‘an advancement’ in simplifying drone surveying processes and point cloud data processing