ALE completes bridge installation

13 February 2018

Global heavy lift service provider ALE has completed the load-out and installation of a bridge in Belgium, using its Mega Jack 800 jacking system. The Brug van den Azijn bridge weighed 1,200 tonnes and measured 124 metres long.

Image 1

The ‘Brug van den Azijn’ bridge jacked-up using the ALE’s Mega Jack 800

The first stage involved the load-out of the bridge deck, where it was transported by barge from Wondelgem, Ghent, to Antwerp. Due to low bridges on route, the arches of the Brug van den Azijn bridge were transported in pieces.

When the barge arrived in Antwerp, the bridge was loaded-in on a site near the final location. Here the arches were fully assembled. The entire bridge structure was then loaded-out and transported 2.5 km by barge to the final installation location.

It was then installed using ALE’s Mega Jack 800 to jack-up the bridge deck 8 metres and position it higher than the abutments. The bridge was then lowered by 3 metres in between the abutments and into its final position.

Tom Van De Locht, project engineer, said, “This was a challenging bridge installation project which demonstrates our capabilities and application of different techniques. By using our Mega Jack 800 system, operational time was reduced, and it was easily integrated on site because of its small footprint and compatibility with our other services to perform the full turnkey installation solution.”

The job was undertaken for government agency De Vlaamse Waterweg which manages the waterways in Flanders. The job was carried out in within two weeks, said ALE.

Image 2

Image 2

Latest News
EquipmentShare mulls US IPO in 2025
Construction equipment rental company equipment share could go public as early as next year (2025), according to a report by Bloomberg.
New Teupen spider for multiple markets
Product aimes at US market follows Teupen’s acquisition by Altec
Dragon crushers continuing to gain in popularity
Company owner and director presents the CR400 model to Intermat crowds