Climbing above 800 feet

16 September 2009

The top tie-in in position just below the climbing cage

The top tie-in in position just below the climbing cage

A tower crane company in Canada has erected three large luffing jib towers, two of which will be climbed to a final height of more than 800 feet (244 m) using tie-ins more than 60 feet (18 m) long.

All three cranes erected on the Calgary, Alberta site in July are Terex Comedil CTL630 luffers from Oxford Builders, the tower crane division of EllisDon Construction.

The building's structure is steel with a concrete core. "The cranes need to have four sets of large tie-ins, with struts in excess of 60 feet long," explains Mike Demelo, vice president, equipment, EllisDon Construction. "After each crane is climbed and has its four sets of large tie-in struts, the bottom set will be cycled to the top and a small set will be inserted into the structural steel," Demelo continues.

Latest News
Ausa looks to the future with electric machines
OEM plans new machines by 2025
Kaeser shows ‘study’ for electric compressor
Machine produced to generate discussion about electric products
Hochtief subsidiary increases stake in mining services firm
Hochtief’s Australian subsidiary Cimic has increased its stake in mining services company Thiess, in response to the importance of the energy transition.