ALE transports submarine

19 August 2019

Heavy lift and transportation specialist ALE has completed the launch of the KRI Alugoro (405) submarine in Indonesia.

Weighing 1,331 tonnes, ALE transported the submarine from the fabrication shop to the quayside using 60 axle lines of self propelled modular transport (SPMT).

ALE then provided the winches and ballasting required to load-out the 61 metre long submarine onto a barge and sea-fastened it to the deck.

ALE sub

The submarine weighed 1,331 tonnes

ALE towed the barge to a dry dock and then transferred it to a floating dock. The floating dock enabled the submarine to be repositioned before it was set down on a pontoon and then floated. It was then officially launched at a designated pier.

ALE performing the submarine launch operation in South East Asia

ALE performed the submarine launch operation in Indonesia

The manoeuvres were performed using sixteen 150 tonne capacity climbing jacks, twelve 400 tonne per hour capacity ballast pumps and four 8 tonne capacity precision winches.

ALE said one of the project’s challenges was working within the tidal windows. The company operated both day and night shifts to facilitate efficient time management, and as a result completed the project more than four days ahead of schedule.

KRI Alugoro was the final vessel to be commissioned as part of a US€1.2 billion contract for three diesel-electric submarines, between Daewoo Shipbuilding and Marine Engineering (DSME) and the Indonesian Ministry of Defence.

The KRI Alugoro being transported onto the floating dock

The KRI Alugoro measures 61 metres long

Latest News
EquipmentShare mulls US IPO in 2025
Construction equipment rental company equipment share could go public as early as next year (2025), according to a report by Bloomberg.
New Teupen spider for multiple markets
Product aimes at US market follows Teupen’s acquisition by Altec
Dragon crushers continuing to gain in popularity
Company owner and director presents the CR400 model to Intermat crowds