The 26.5 US ton (24 tonne) Potain MR 415 on site in Chicago

The 26.5 US ton (24 tonne) Potain MR 415 on site in Chicago

James McHugh Construction put a Potain MR 415 tower crane up on the busy streets of Chicago, USA, using an existing building as a foundation.

The tower crane has been erected on top of Block 37 in Chicago. The building is having a 34-storey apartment building constructed on top of the existing five-storey complex.

McHugh began lifting work on the tower in June 2014. The 26.5 US ton (24 tonne) MR 415 was rented from Central Contractors (Central) in Crestwood, Illinois, a branch of the All Family of Companies (All), headquartered in Cleveland, Ohio.

The MR 415 was chosen because of its ability to work in small working areas, Paul Urbanski, Central sales manager, said. “The MR 415 was initially erected on 11 tower sections so that its jib would clear the historic Cadillac Theatre, which is just across the street, when it was stowed,” Urbanski explained. “With a lack of space below for a spread foundation, the crane was tied in at the 5th floor (a height of 23 metres) during the initial assembly to reduce the foundation reactions.”

A 550 ton capacity Grove GMK7550 with 121 feet (37 m) of luffing jib was used to help erect the MR 415.

“The unique thing about the Block 37 project is that before the concrete construction could begin, 6 m tall steel trusses with segments that weighed as much as 40 tons [36 tonnes] were erected on the roof to support the additional 34 floors of construction,” Urbanski said.

With the trusses installed the MR 415 was used to lift construction materials for the job. The heaviest lifts weighed 10 tons (9 tonnes) at heights up to 142 m. Urbanski said the MR 415’s single part line capability was an added plus on the job, as it gave McHugh’s operator approximately 9.4 tons (8.5 tonnes) at 50 m and approximately 13.2 tons (12 tonnes) at 3.5 m.

The new tower at Block 37 will have 690 apartments, making it one of the tallest apartment buildings to be constructed in Chicago’s loop in decades. The complex will include an outdoor pool and spa, rooftop spa and fitness centre.

Latest News
Jury concludes that Caterpillar owes $100m to importer amid US lawsuit
A jury in the US has concluded that Caterpillar must pay $100 million to an importer, following a legal dispute between the two companies.
Kanamoto eyes North America move
Company aims to double overseas revenue in next six years
Smart Construction to unveil Edge 2 at Intermat
New launch ‘an advancement’ in simplifying drone surveying processes and point cloud data processing