Dam supports
17 June 2011
Ten Manitowoc cranes are working on the construction of a remote dam in South Africa.
The De Hoop ('The Hope') Dam will be 81 m tall and stretch more than 1 km over the Steelpoort River in Limpopo, South Africa. It is being built for the South African Department of Water Affairs.
The Manitowoc cranes on the project are a mix of Potain tower cranes, a Manitowoc crawler crane and Grove mobile cranes. The cranes are performing a range of tasks, which will change as the project progresses. But all work is related to constructing the outlet works of the dam, which will require 930,000 m3 of concrete to complete. Jobs include assembling conveyors and concrete batching plants, placing shuttering and reinforced steel, installing mechanical items in the outlet works, damage recovery and pouring concrete.
The location and terrain are two major challenges on site. The dam sits in the middle of an untouched rural landscape, in a river valley with steep slopes of loose soil running either side. To complicate matters, a river diversion also runs through the site.
Henry Wells, managing director at Crane Load Tech, said the company had to construct roads to ease transport of the mobile and crawler cranes.
"We are used to working on job sites with restricted access, but De Hoop is among the most extreme," he said. "On the project we've built temporary access roads across the slopes and contours so the cranes can travel the undulating terrain. We were able to maneuver the cranes to where they can offer maximum coverage and the most efficient delivery of materials."
A 25 tonne capacity Potain MD 485 B is pouring the majority of the concrete. For smaller lifts, there is also a 4 tonne Potain Igo 50 self-erecting crane.
From the company's crawler crane line there is a 90 tonne Model 10000, designed for simple erection, reliability and easy operation. The Grove mobile cranes on site include the truck-mounted TMS700E, which has a 60 tonne capacity and the 60 tonne RT760E and 30 tonne RT530E from the rough-terrain crane line. There is also a Yardboss industrial crane, the YB4409XL, which has an 8 tonne capacity.
The cranes arrived on site in April 2009 and will remain on site for another two years. The South African Department of Water Affairs is building the dam as a bulk storage facility to supplement Limpopo's current water supply. Its reservoir covers 1,690 hectares. The dam will be complete by August 2012.