29 April 2008

Us: Constructing the foundation raft for the new 42 storey Washington Mutual Bank in Seattle, US called for 7800 m3 of concrete to be placed during a 17 hour continuous pour.

Brundage Bone Concrete Pumping used six Schwing truck mounted concrete pumps, supplied by a fleet of 80 concrete trucks, to place the concrete for the 2.5 m thick raft.

Roads surrounding the site, which is part of the Seattle Art Museum extension, had to be closed to position the S 58 SX, S 47 SX and four S47 SX boom pumps around the 70 by 73 m site. Now the foundation raft is complete, Brundage is using a Schwing BP 8800 stationary pump and a KVM 39 X boom to place concrete for the elevator core, columns and deck of the steel framed structure.

Latest News
Multitel Pagliero opens subsidiary in Spain
Newly established Multitel Iberica to provide direct sales and service 
ESTA launches a manifesto for transport
European association sets out five year plan for abnormal road transport
MyCrane passes 10,000 crane milestone
More than 10,000 cranes now available to rent via online platform