An ambitious 16km railway tunnelling project near the town of Wiesing, in the Austrian Tyrol, took place earlier this year. Part of the Inn Valley Austrian Railways project involved the construction of a 30m deep rescue shaft, close to a rock face, with the use of an AB 2000 feeder and rock drilling unit from Wimmer.

"This rock face had to be stabilised with numerous rock anchors 6 to 8 m in length so that safe work on the bottom was possible," said Wimmer International's Martin Gasser

He continued, "The drill was put on a truck-mounted crane by a special adaptor. The oil supply of the unit was managed by an excavator at the ground through 50 m of conduits. The operators worked at a lifting platform beneath the drill. Every few minutes new rods needed to be added to reach the required hole depth."

Latest News
Jury concludes that Caterpillar owes $100m to importer amid US lawsuit
A jury in the US has concluded that Caterpillar must pay $100 million to an importer, following a legal dispute between the two companies.
Kanamoto eyes North America move
Company aims to double overseas revenue in next six years
Smart Construction to unveil Edge 2 at Intermat
New launch ‘an advancement’ in simplifying drone surveying processes and point cloud data processing