Maxim purchases new Terex SK 575

07 July 2011

Maxim Crane Works recently purchased a new Terex SK 575 tower crane as part of a full turnkey package to support general contractor Turner Construction's project at the Good Samaritan Hospital Medical Office Building, Cincinnati, OH. The original crane reserved for the job was held up on another jobsite, requiring Maxim to purchase the new crane quickly and Terex to deliver it to the jobsite within approximately six weeks.

The project, involving the construction of an eight-story building, was awarded to Maxim Crane Works at the end of January and started on March 1, 2011. The Terex SK 575 hammerhead tower crane was recommended by Maxim Crane for its fast assembly, lifting capacities and line speed to match the strict jobsite planning, performance and production requirements.

Located in the area of the University of Cincinnati, just off a busy main thoroughfare, the primary challenge on this restricted, urban jobsite was its tight "just-in-time" assembly schedule. Set within 100-feet of an open lane of heavy traffic, the observation of strict traffic control and precise planning requirements were critical to the successful assembly of three cranes within the allocated two-day window..

Matt Hyden, operations manager for Maxim's tower crane division said, "For us, the question of schedule had grown two-fold. In addition to the existing planning requirements, the crane was going to be new."

Maxim needed to assure Terex could ensure delivery of the complete upper-works ready to ship within just 45 days of our customer's order. Maxim would then be able to assemble and test-run all functions prior to operation and load-test. Hyden said the process went precisely as planned.

The first truck from the Terex Cranes Wilmington production facility arrived in Cincinnati on the morning of February 26 and the last load arrived around 5.30 p.m. the same day. A 500-ton hydraulic crane with luffing jib and 70-ton assist crane, to assemble the larger 500-ton machine, were required to erect the Terex SK 575 to its full 195 feet (59.4 meter) freestanding height.

Maxim Crane crews worked from dawn to dusk on Sunday, February 27 to get the crane erected and fully load-tested. By Monday morning, the SK 575 was erected on-time and ready to undergo the customer's third-party safety inspection, which it passed with no deficiencies.

"Prior to the bid, we worked with the general contractor to assist in selecting the best crane model and configuration based on their lifting requirements," said Hyden. "Since we already own about 75 Terex SK series hammerhead tower cranes, we're quite familiar with their excellent capabilities, as well as their record for reliability."

Hyden said the Terex SK 575 enabled preparation without shutting down traffic due to safety concerns, or impacting overall project planning. "The SK 575 turned out to be the perfect fit on a jobsite that is making great progress, exactly according to schedule," Hyden said.

Erected to a hook height of 195 feet with 213-foot jib length in 2-part line configuration, Maxim Crane Works' latest Terex SK 575 hammerhead tower crane is currently handling from 25 to more than 50 lifts daily. Primarily used for general hoisting duties, unloading trucks of rebar, pouring concrete or setting structural steel and precast work, as configured, the crane is capable of lifting a maximum of 35,200 lbs at 107-foot radius and 15,400 lbs at its maximum reach of 213-feet. Its heaviest lifts at the Good Samaritan site have been precast panels weighing up to 20,000 lbs. at a 170 foot radius, and 15,000 lb. panels out to 213 feet.

Latest News
Jury concludes that Caterpillar owes $100m to importer amid US lawsuit
A jury in the US has concluded that Caterpillar must pay $100 million to an importer, following a legal dispute between the two companies.
Kanamoto eyes North America move
Company aims to double overseas revenue in next six years
Smart Construction to unveil Edge 2 at Intermat
New launch ‘an advancement’ in simplifying drone surveying processes and point cloud data processing