Milestone reached in Optara project

09 March 2015

Tailing of the main fractionator from horizontal to vertical position

Tailing of the main fractionator from horizontal to vertical position

Lift service provider Aertssen Kranen and heavy lift and specialized transport service provider ALE have finished installing the main fractionators at the Optara project in Antwerp, Belgium.

The Optara project forms part of a €1 billion (US$ 1.1 billion) investment from Total at the refining and petrochemical complex in Antwerp. Work at the site will include the construction of a new unit and the conversion of an existing unit, a spokesperson said.

The main fractionators weighed 250 tonnes and measured 57 metres long and had a diameter of 10 m. It was moved to position using 32 axle lines of self propelled modular transporter (SPMT). Once in position, a 650 tonne capacity Terex Superlift 3800 crawler crane was used to lift and install the fractionators. A 280 tonne Hitachi SCX2800-2 crawler crane was used as a tailing crane.

Latest News
Another record quarter for Herc Rentals
Equipment rental revenues up 10% over 2023 Q1
Is better progress management the secret to successful projects?
Jean Luc Ozoux looks at why some companies report that they have not met planned timelines or budgets
Former FIEC director general Ulrich Paetzold dies
Former director general of the European Construction Industry Federation (FIEC) Ulrich Paetzold passed away on 20 April.