Mumbai load out marathon

09 March 2012

Living quarters for 275 people, weighing 4,400 tonnes. Five rows of SPMT were used with 184 axles an

Living quarters for 275 people, weighing 4,400 tonnes. Five rows of SPMT were used with 184 axles and 1,460 tyres, bringing the total weight up to 5,300 tonnes

Lift and Shift has carried out the transport and load out of 20 components for the rebuilt Mumbai High North Offshore Platform.

The India-based lifting and transport specialist spent two years planning the project, which included moving the deck, living quarter modules, bridges, jackets, tripods and process and technical platforms.

Lift and Shift bought in new SPMT and ballast pumps to handle the components, the largest of which required 204 axle lines. In January 2012 five of the biggest modules, weighing between 3,300 and 4,500 tonnes, were transported from the fabrication yard to the jetty and loaded out on barges by rolling them on with the rising tide.

Some of the load outs had to be carried out during the night, which required additional safety checks due to tidal restrictions in the Hazira channel. The load outs were executed along the length and width of the barge at the Lift and Shift jetties.

The project was carried out over 75 days. Total weight of all the structures was 40,000 tonnes.

Latest News
Latest episode of Construction Briefing podcast now available
New episode of Construction Briefing podcast focuses on Ukraine 
Sany America rolls out new RT
At the ARA show in New Orleans last month, Sany debuted a new 55-ton capacity rough terrain crane.
Peri debuts new formwork system
In response to a surge in U.S. construction, Peri USA has develoed a new formwork solution that caters to various size ranges for wall, column, and slab formwork