Shipyard lift for ALE

18 September 2014

The AL.SK190 was configured with a 118.5 m main boom. In this configuration it carried out three lif

The AL.SK190 was configured with a 118.5 m main boom. In this configuration it carried out three lifts over a ten day time frame

Heavy lift and transport company ALE transported and lifted an accommodation module and a service module in Rio de Janeiro, Brazil.

The accommodation module weighed 1,538 tonnes and the service module weighed 702 tonnes. Both modules were installed on the Petrobras P-74 FPSO at the Petrobras shipyard, Rio de Janeiro.

The modules were lifted using an AL.SK190 crane. With its ring base there is a 35 x 35 metre footprint and lifting capacity is 4,300 tonnes, ALE said. Maximum boom height is 200 m and its maximum load moment rating is 196,000 tonne-metres.

The AL.SK190 was set up with a 118.5 m main boom. In this configuration it carried out three lifts over a ten day time frame. Site moves were carried out using 56 axle lines of self propelled modular transporter (SPMT).

Giovanni Alders, ALE sales manager, said, “Using the AL.SK190 crane saved up to two months in downtime as our customer did not have to take the FPSO out of the dock. The actual lifting time to install the two modules was reduced to two weeks and modifications on the FPSO could still go ahead while the crane was being assembled and disassembled.”

Latest News
Jury concludes that Caterpillar owes $100m to importer amid US lawsuit
A jury in the US has concluded that Caterpillar must pay $100 million to an importer, following a legal dispute between the two companies.
Kanamoto eyes North America move
Company aims to double overseas revenue in next six years
Smart Construction to unveil Edge 2 at Intermat
New launch ‘an advancement’ in simplifying drone surveying processes and point cloud data processing