French nuclear project hit by more delays

Premium Content

10 October 2019

flamanville nuke

The Flamanville nuclear reactor

Electricite de France (EDF) says repair work on faulty welding at the Flamanville nuclear plant in northwest France will cost €1.5 billion.

The additional work will push the total cost of the project up by some 4%, to approximately €12.4 billion.

The repair work was demanded by the French nuclear watchdog ASN, following inspections; now EDF says its preferred approach to the repairs is to use robot welding.

The new welding, however, is unlikely to be ready for inspection by ASN before the end of 2020.

In a statement, EDF said, “The provisional schedule…results in the date of fuel loading at the end of 2022.” This would mean the reactor coming online some time in 2023 – four years later than initially anticipated.

EDF shares fell 1% following the news and are down more than 36% this year, adding to the company’s woes, which include delays and cost hikes on two similar reactors in the UK.

The evolution of electromobility in construction
The case for electric construction equipment is now as much about productivity and business value as it is about sustainability
Why crawler AWPs are becoming essential to modern mining and tunnelling
While excavators, loaders and TBMs dominate the spotlight, crawler aerial work platforms are quietly transforming how mining and tunnelling projects are built, maintained and operated.
Beyond the logo: Why content is the engine of successful B2B brand transformation
KHL Content Studio’s Jon Abrahams on how a new identity may capture attention, but it’s understanding that builds trust