ALE on France’s first floating wind turbine

Premium Content

03 January 2018

Global heavy lifting and transport contractor, ALE has completed the installation of wind turbine components for France’s first floating wind turbine, Floatgen, at Saint Nazaire, Brittany.

Image 1

ALE was contracted by French floating offshore wind specialist Ideol – the company behind the design and engineering of the floating foundation – to perform the mechanical and electrical completion of a 2MW V80 wind turbine generator onto a floating foundation.

Each component was lifted using a 1,200 tonne capacity crane. There were two tower sections; a nacelle; a hub; and three blades. A 100 tonne capacity auxiliary crane was also required to erect and lift the two tower sections in tandem.

Image 2

To maintain the stability of the floating foundation, ALE simultaneously performed foundation ballasting operations during the lifting operation. Four submersible pumps were used to supply water to the ballast tanks situated at the corners of the floating foundation.

Once the wind turbine was fully mounted on top of the foundation electrical components and cables were connected and assembled and the client’s sensors and measuring equipment installed.

Antonio Martin Garcia, ALE project manager, commented, “This was a unique job for ALE and the first time we have undertaken such a complex scope of work in this sector. We were able to provide a bespoke solution for this challenging operation and by providing experienced operators with expertise in each discipline, including the installation, ballasting, and lifting, as well as coordination we could ensure smooth project management.”

 

Southwest Industrial Rigging gets new owner and leadership team
Entering a new era but aspiring to continue Harry Baker’s legacy
Trail King debuts automatic kingpin steering trailers
New trio hailed as a fundamental shift in heavy-haul equipment design
How a modular test system overcame a genset bottleneck
When rising demand threatened to outpace a genset manufacturer’s testing capacity, a modular test cell bridged the gap – and laid the groundwork for future growth.