Lifting a TBM from the sea

11 December 2017

Specialist pipeline contractor Stockton Drilling has completed multiple component lifts of a 28 tonne, 18 metre long tunnel boring machine (TBM) that was working subsea at the Beatrice Offshore Windfarm / Direct Pipe Landfalls (BOWL) project at Portgordon, Scotland.

The BOWL project will produce 584 megawatts from 84 turbines in the outer Moray Firth, powering approximately 450,000 homes at a cost of £2.6 billion to its investors SSE, Copenhagen Infrastructure Partners and Red Rock Power.

Stockton’s scope of work included the trenchless installation of two independent 48 inch x 450 m steel landfalls for high-velocity cables by utilising Herrenknecht’s DirectPipe system and AVN1000 micro tunnelling machine. DirectPipe, a hybrid micro-tunnelling and pipe-jack system that lines the tunnel as it advances, was used due to the site’s un-drillable geology.

In a world-first, the TBM was recovered from the sea after each drive using a remote disconnect module. Divers were then dispatched to the TBM’s location to attach a 34 tonne capacity, 16.6 m-long beam so a 120 tonne capacity crane, placed on a rented jack-up barge, could lift it out of the water and place it on a multi-cat for return to Buckie Harbour.

UK spreader and lifting beam specialist Modulift designed and manufactured the below-the-hook solution to lift the TBM from beneath the surface, where it was positioned four degrees from horizontal. The TBM is made up of ten modules that each have their own individual lifting points. All these were utilised to provide equal loading and enable the machine to be lifted in one piece. The beam also had three top lifting points to facilitate rigging to the crane.

Modulift used counterweights so the beam tilted when unloaded to give it the same inclination as the load on the seabed, ensuring all bottom connections were carrying load. The beam, however, had to lift the TBM level. It was also manufactured to withstand the dynamic forces present in the demanding, marine environment.

Patric Ridge, business development manager at Stockton Drilling, said, “The product satisfied the requirements and standards set out at the beginning of the project. Lifting [the TBM] in one piece was a swifter, safer and more efficient process. Weather conditions had to be just right to perform the lift, so the lift had to be completed in a timely and safe manner. The process was further complicated by the low depth of water [less than 10 m] in the area.”

Ridge explained that the TBM was submerged for less than 48 hours for each 420 m drive, approximately half-a-mile offshore. Surface alluvial comprising pebbles and cobbles, overlaying bedrock of weathered sandstone, prevented the use of more traditional horizontal directional drilling methods. Further, the beach area around the landfall site is a designated Site of Specific Scientific Interest (SSSI).

Stockton has retained the beam for further use.

 

Latest News
Latest episode of Construction Briefing podcast now available
New episode of Construction Briefing podcast focuses on Ukraine 
Sany America rolls out new RT
At the ARA show in New Orleans last month, Sany debuted a new 55-ton capacity rough terrain crane.
Peri debuts new formwork system
In response to a surge in U.S. construction, Peri USA has develoed a new formwork solution that caters to various size ranges for wall, column, and slab formwork