ALE transports turbine components

10 August 2018

International lifting and transport specialist ALE is performing the transport, craneage and installation of 20 Siemens Gamesa wind turbine components to Vena Energy’s Tolo 1 project site in Jeneponto, South Sulawesi, Indonesia.

As part of the contract, ALE was tasked with providing the full TCI package of 20 Siemens Gamesa wind turbines comprising five tower sections, to make up a total of 220 abnormal loads.

Components were received at the Makassar Port, where they were unloaded and stored. The generators, weighing 74 tonnes each, and the tower sections, the heaviest weighing 86 tonnes, were loaded onto 11 axle lines of conventional trailers in a configuration of 3 x 2 file 5 as well as 6 axle lines of clamp tower trailers. This is the first time these specialist clamp tower trailers had been used in Indonesia and were ideally suited when negotiating the overhead restrictions on the challenging route as the driving height could be reduced, said ALE.

For the 64-metre-long blades, 12 axle lines of specialist extendable blade trailers were utilised in a configuration of 3 x 2 file 4 axles.  

At the time of writing ALE had transported 40 per cent of the components almost 100 km to the site.

 

Latest News
The future of the lattice boom crawler market
A host of challenges have given the lattice boom crawler crane market fits and starts in 2024.
Movers and shakers: 5 electric construction machines introduced so far this year
Here’s a look at some of the latest electric-powered earthmovers and material handlers to hit the market since the start of 2024
Reviewing the Tower Cranes North America Conference
Alex Dahm and D.Ann Shiffler provide an overview of the Tower Cranes North America Conference in Nashville, TN.