Awards Shortlist – Contract under US$1 million

16 October 2017

Judges: Henrik Bonnesen, Cowi, Denmark; Dan Costello, Costello Dismantling, USA; Jim Graham, Winter Environmental, USA

C&D Consultancy, Apex Group (United Kingdom)

Project – Alltech Stamford

Client – John Paul Construction

Apex and C&D Consultancy were set a number of technical challenges in what seemed to be a relatively straight-forward demolition of a steel frame building for John Paul Construction.

Careful planning and using each other’s strengths proved critical in meeting the stringent timelines and the smooth execution of the demolition, while being mindful of environmental considerations and the small matter of preserving a US$2 million treasure chest of Japanese artefacts during the work.

Ceres New Zealand

Project – Deconstruction of Haywards HVDC Pole 1 Building

Client – Transpower New Zealand

Ceres New Zealand was contracted for the demolition of Pole 1 Building at Haywards HVDC station through a competitive tender process in December 2016.

The scope of work included asbestos cladding removal, dust and sediment controls, demolition of Pole 1 Building, demolition of cable tunnel, crushing concrete debris, backfilling basement, installation of switchyard aggregate and installation of monitoring wells.

Ginlee Construction (Singapore)

Ginlee

Ginlee Construction flies the flag for Singapore in the Contract under US$1 million category

Project – Kwong Wai Shiu Hospital

Client – Guan Ho Construction Co

The Kwong Wai Shiu Hospital project was especially challenging as the building is a government certified conservation site. This regulation posed a challenge to the demolition works and through careful planning, good foresight and innovative machines, the team was able to meet the owner’s needs and complete the project.

The main challenge was to demolish the internal structure of the building while retaining the façade. The presence of live buildings and nursing homes in the area also required a more controlled demolition procedure. The team thus chose not to hack the whole structure, but used cutting and crushing for structures close to the facade to minimise noise and vibration transfer

Priestly Demolition (Canada)

Project – St Michael’s Hospital Redevelopment

Client – Bondfield Construction Company (owner IO)

Priestly Demolition was contracted to perform the demolition of the existing 17 storey stair tower which was land or “building” locked within the existing functioning hospital. The only access to the work was by foot or tower crane. Priestly’s demolition plan called for the use of the on site tower crane. The obvious challenge with demolishing a stair tower is that nothing is level, so Priestly designed and fabricated a self-levelling platform to work from. This platform was installed and moved down through the floors as we went, helping us make short work of the removal.

 The World Demolition Awards are part of the World Demolition Summit, which takes place in London, UK on Thursday November 2. The event is organised by Demolition & Recycling International in co-operation with the European Demolition Association and with the support of the National Demolition Association of the USA. The headline sponsor is Volvo Construction Equipment.

For more details please visit www.demolitionsummit.com

Latest News
EquipmentShare mulls US IPO in 2025
Construction equipment rental company equipment share could go public as early as next year (2025), according to a report by Bloomberg.
New Teupen spider for multiple markets
Product aimes at US market follows Teupen’s acquisition by Altec
Dragon crushers continuing to gain in popularity
Company owner and director presents the CR400 model to Intermat crowds