19 March 2008

Austrian Contractor Gerstl Hasused Doka's new TLS (Table Lifting System) during construction of the new Austrian Airlines Group Headquarters (Office Park II) at Vienna Airport, Austria.

About 190 Doka tableforms were needed to form the floor slabs, with each of the 2200 m2 upper floors cast in a weekly cycle. Up to 500 m2 of slab was formed per day.

With a very tight construction schedule, and the large number of tableforms needed, the new Table Lifting System moved the tableforms from one floor to the next without any crane assistance.

The tableforms were moved from their original position using Doka's “shifting trolley” and wheeled onto TLS's platform, with each lift taking about 20 seconds. Once all the tableforms for one section were moved to the floor above the TLS was raised by crane to the next floor.

Inside Zoomlion’s Smart Factory: How digital manufacturing could rewrite the rules for heavy equipment
Zoomlion’s new excavator factory in Changsha is not simply faster or more automated than traditional plants; it represents a fundamental rethink of how construction equipment can be designed, built, and delivered
Donaldson to lift the lid on ArmorSeal in upcoming webinar
Expert panel will discuss new air filtration technology designed to improve durability, serviceability and performance – February 19.
First expert speaker announced for power transition webinar
Moog Construction’s Dr Nate Keller to join panel for February 17 event