Guay pairs up for kiln lift

06 September 2016

The Manitowoc 16000 and MOD 250/300 beam combine to lift a 280 tonne clinker kiln section

The Manitowoc 16000 and MOD 250/300 beam combine to lift a 280 tonne clinker kiln section

Canadian crane rental and specialized transport company Guay chose a pair of lattice boom crawler cranes with spreader beams for a project to install a six-section clinker kiln in Québec.

Equipment Guay used included Manitowoc 16000 and 2250 crawlers and Modulift spreader beams for the McInnis Cement plant development project at Port-Daniel-Gascons.

Lifting operations were carried out in early spring but equipment still had to withstand extreme weather on the Canadian coast, including heavy snowfall. Lift planning had to account for the changes in conditions and constantly evolving jobsite environment.

This important industrial project is scheduled for completion later in 2016. McInnis said that it will be a “model of environmental performance”, meeting the highest standards.

The six pieces were assembled in pairs at ground level before the resulting sections were lifted and assembled in three subsequent lifts. Two were lifted using the 16000 fitted with a Max-er attachment that allows the crane to lift more at a longer radius. The 2250 lifted the other pair. Lifting operations concluded with a tandem lift using both cranes to align the three sections in their final positions.

A pair of Modulift MOD 250/300 beams were used at spans of 12 metres for each lift, including the heaviest kiln section that was 280 tonnes and 26 m long. The 16000 was rigged with 54 m boom and 150 tonnes plus 54 tonnes of counterweight. The wheeled Max-er carried 232 tonnes of ballast. The 2250, meanwhile, had a boom length of 52 m and 113 plus 54 tonnes of counterweight. Both cranes lifted the heaviest loads at about 9 m radius.

Rafael Palomar, team leader in Guay’s technical department, said, “Our scope of work for the project covered all lifting-related requirements, including selection of cranes and rigging equipment, ground preparations and logistics, in addition to lift co-ordination and supervision. Given the demands of the project combined with the weather, selecting suitable, durable equipment was essential to delivering our commitment to the landmark project.”

Palomar explained that the Modulift beams were chosen because of their capacity and span plus the ease with which length could be adjusted onsite. To lift the sections to their final positions at the right angle, rigging equipment had to be adjusted according to the centres of gravity, as calculated during the planning stages.

Latest News
Non-residential projects bolster crane activity in Australia
Latest RLB Crane Index survey for Australia shows strength in civils and infrastructure sector
Current affairs: Clark Rigging uses gantry system for Erie Canal lock repairs
How Clark Rigging used a specially-designed gantry system to repair lock gates on New York state’s historic Erie Canal 
Tadano crawler powers Toggenburger’s bridge lift
The Swiss crane service provider overcame tight space constraints and delicate load requirements to complete the project