As part of the redevelopment of St Pancras railway station in London, England, a way had to be found to remove three maintenance gantry platforms from the inside of the Victorian roof. Mobile cranes could not be used because of the point loading over underground tunnels. In addition, the historically important building is Grade 1 listed, meaning that no lifting gear could be rigged to the roof in case of damage.

Technical Cranes' solution was to suspend a series of 2.5 tonne SWL Yale electric chain hoists from the platform's runway beams, using Yale CTP trolley beam clamps, and connect them to the platforms on their original lifting lugs.

The two 16 tonne gantries were lowered on eight of the hoists while the third, weighing 19 tonnes, required 10. A control panel was custom-built that could either synchronise the hoists or allow them to be adjusted individually while lowering the platforms from the 30 m high roof.

Parked in plane sight: Why GSE fleets rely on large spark-ignited engines
Examining how proven technology can help airport fleets balance uptime, cost, flexibility and lower emissions
Accessing aging infrastructure: Choosing the right AWP for the application
How site conditions determine which aerial work platform is best suited to the project
The evolution of construction site safety: Why smart machines matter
Intelligent intervention that can help contractors prevent incidents without compromising productivity