ic120725.xml

Premium Content

11 April 2008

In April ALE was tasked with lifting the 500 tonne arched centre section of the Vicaria Bridge in Albacete, Spain. The operation was carried out using an auxiliary steel structure comprising beams supported over each transverse girder of the lateral spans. Four 200 tonne capacity HLS200 strand jacks were installed on the auxiliary sections.

The lifting began by progressively taking of the load until the central span of the arch was detached from its temporary supports. Following a topography test, the arch section was levelled and the four units began their simultaneous 40 m lift.

When the central span was close to its final elevation, another topography test was carried out. The span was then lifted into its final position and connected to the outer bridge decks. The job was completed in one day.

Truckstop.com and ProMiles partner up to streamline heavy haul quoting
Truckstop.com and ProMiles have expanded the Heavy Haul Load Board with route-based quoting for oversize and overweight freight.
SCRA issues statement on tariff ruling by Supreme Court
Industry association comments on US ruling overturning import tariffs
Mi-Jack acquires new facility in Illinois, USA
New 200,000 square-foot production facility to meet critical capacity needs