In April ALE was tasked with lifting the 500 tonne arched centre section of the Vicaria Bridge in Albacete, Spain. The operation was carried out using an auxiliary steel structure comprising beams supported over each transverse girder of the lateral spans. Four 200 tonne capacity HLS200 strand jacks were installed on the auxiliary sections.

The lifting began by progressively taking of the load until the central span of the arch was detached from its temporary supports. Following a topography test, the arch section was levelled and the four units began their simultaneous 40 m lift.

When the central span was close to its final elevation, another topography test was carried out. The span was then lifted into its final position and connected to the outer bridge decks. The job was completed in one day.

2027 European Rental Awards open for entries
Includes new awards category for ‘People’ initiatives. Deadline for entries is 26 February 2027.
WorkDry invests in pump fleet in preparation for extreme events
Company adds hundreds of new pumps in anticipation of extreme El Niño weather events.
Smarter by design: How intelligent excavators are delivering better jobsite results
Integrated technology is helping contractors improve accuracy, productivity and control without neglecting the fundamentals of machine performance