Largest hard rock TBM built for US

09 January 2020

Big Tex Robbins Company 1

The Robbins Company has completed the assembly of ‘Big Tex’ - said to be the largest hard rock TBM ever to be used in the US.

Tunnelling equipment manufacturer The Robbins Company has finished the assembly of what it describes as the largest hard rock tunnel boring machine (TBM) in the US.

Named ‘Big Tex’, the Robbins Main Beam TBM was designed with a diameter of 11.6m and, thanks to its a dual-diameter aspect – and a conversion process that is believed to be the first-of-its kind – can even reduce its diameter to just 9.9m partway through tunnelling.

Designed for joint venture company Southland/Mole, Robbins said that the unique TBM will be used to excavate an 8km long drainage tunnel, comprised of two different diameters, as part of the Mill Creek Tunnel Project.

The project aims to provide 100-year long flood protection for the east and southeast regions of Dallas in the state of Texas, for which ‘Big Tex’ was named.

“The completion of the TBM assembly marks a major milestone in the Mill Creek Tunnel Project,” said council member Lee Kleinman, chair of the Transportation and Infrastructure Committee for the City of Dallas. “I’m thrilled to see this type of engineering marvel happening right here in Dallas.”

 

Big Tex Robbins Company 2

The adaptable machine will change size partway through the bore, to a more compact 9.9 m (32.5 ft) in diameter.

The adaptable machine will change size partway through the bore, to a more compact 9.9m in diameter.

The dual-diameter aspect of the TBM comprises a specialised cutterhead with removable spacers and adjustable bucket lips. According to Robbins, contractor Southland/Mole will make the conversion to the smaller diameter underground at approximately 2.8km into the bore. This will be done after the machine has completed the drilling of the 11.6m diameter section.

The company said this will create as “upstream section of the tunnel is designed with a circular cross section and peak flow rate of 42m3/sec, while the downstream 2.8 k portion has a higher peak flow of 565m3/sec.”

Excavation of the Mill Creek Drainage Relief Tunnel will see the TBM in operation for 24 hours a day. It will bore through 25m of Austin Chalk day, at depths ranging from 31 to 45m below the city of Dallas.

The project is due for completion in 2023.

.

Big Tex Robbins Company 3

The 8 km (5 mi) Mill Creek Drainage Relief tunnel will provide 100-year flood protection for east and southeast Dallas, areas affected in recent years by severe storms.

Big Tex Robbins Company 4

The Robbins TBM will undergo a ‘first of its kind’ diameter conversion roughly 2.8 km into the bore.

 

 

Latest News
Kaeser shows ‘study’ for electric compressor
Machine produced to generate discussion about electric products
Hochtief subsidiary increases stake in mining services firm
Hochtief’s Australian subsidiary Cimic has increased its stake in mining services company Thiess, in response to the importance of the energy transition.
Hitachi to showcase partnerships
Technology firms work with OEM to develop cutting edge excavators