Layher scaffolding makes A grade

06 May 2014

Layher is providing shoring and scaffolding for construction of a cable-stayed bridge in Germany

Layher is providing shoring and scaffolding for construction of a cable-stayed bridge in Germany

German scaffolding manufacturer Layher is providing scaffolding and shoring support for the construction of an A-frame pylon for a cable-stayed bridge in Germany.

Allround scaffolding and Allround TG 60 shoring frames are being used to complete work on the cable-stayed bridge being built over a railway line in Raunheim, Hesse.

To allow the 55 m high pylon to be built safely, shoring was used to disperse high loads in the area of a binding beam 36 m up. Birdcage scaffolding was also used to provide work platforms and a stairway tower to the A-frame pylon.

The modular scaffolding system provided quick assembly as well as unlimited applications for construction company Wolff & Müller during the project. The prefabricated TG 60 shoring frames were also used.

Bilfinger Schalungsbau was responsible for formwork and scaffolding as well as for planning and material supplies, working in co-operation with Layher’s technical office. Postweiler was brought in as the scaffolding construction company.

Latest News
Crane Institute of America appoints L.D. Stutes as GM
Stutes enters this newly created position with 37 years of experience.
Navigating new immigration policies in the construction industry
Joel Dandrea discusses what construction contractors need to know.
Link-Belt veteran William “Skeeter” Collins announces retirement
Collins, a cornerstone of Link-Belt Cranes’ sales team for over 50 years, will retire in February 2025