Milestone reached in Optara project

By Laura Hatton09 March 2015

Tailing of the main fractionator from horizontal to vertical position

Tailing of the main fractionator from horizontal to vertical position

Lift service provider Aertssen Kranen and heavy lift and specialized transport service provider ALE have finished installing the main fractionators at the Optara project in Antwerp, Belgium.

The Optara project forms part of a €1 billion (US$ 1.1 billion) investment from Total at the refining and petrochemical complex in Antwerp. Work at the site will include the construction of a new unit and the conversion of an existing unit, a spokesperson said.

The main fractionators weighed 250 tonnes and measured 57 metres long and had a diameter of 10 m. It was moved to position using 32 axle lines of self propelled modular transporter (SPMT). Once in position, a 650 tonne capacity Terex Superlift 3800 crawler crane was used to lift and install the fractionators. A 280 tonne Hitachi SCX2800-2 crawler crane was used as a tailing crane.

Latest News
AVL, SuperTurbo partner on hydrogen engine
Companies will explore benefits of mechanically driven turbochargers on hydrogen IC engine
JCB shows new articulated boom at Rental Show
JCB has used The Rental Show to showcase its new AJ48D articulated boom, the second model the company has officially debuted for the North American market
Sany shows telehandler range at The Rental Show
Sany showcased a full range of telehandlers at The Rental Show following its initial debut into the market in 2020