Nigerian move by Cranes R Us

27 November 2020

The 300 tonne structure loaded onto Faymonville G-SL modules arranged side by side

The 300 tonne structure loaded onto Faymonville G-SL modules arranged side by side

When a 300 tonne oil platform module had to be moved contractor Cranes R Us Nigeria Limited chose 24 axle lines of Faymonville G-SL modular trailer.

The structure was for the Anyala Drilling Platform 1 (ANDP1). It had to be moved from the workshop in Port Harcourt, Nigeria, to the quayside. In addition to its weight, the size of the load had to be accommodated. It was 22.5 metres long, 12 metres wide and 9.5 metres tall. Cranes R Us assembled the trailer modules in a 12-line side-by-side configuration.

Cranes R Us used Faymonville G-SL modular trailer, aerial view of load out onto barge at port in Nigeria

Cranes R Us used Faymonville G-SL modular trailer

 

Offshore platform structure for the Anyala Drilling Platform 1

Offshore platform structure for the Anyala Drilling Platform 1

Latest News
PartnerLift expands into Austria
Austria-based Flott Arbeitsbühnen joins German cooperative with its fleet of truck mounts 
Strabag orders pass €25 billion mark despite ‘challenging’ European market
Austrian construction contractor Strabag’s order book has passed €25 billion for the first time
UK government pledges to unblock hundreds of stalled housing construction projects
The UK’s Deputy Prime Minister Angela Rayner has announced plans to get construction work restarted on hundreds of sites across England.