Platform move for ALE

Premium Content

07 December 2015

One support element of the production platform on Scheuerle SPMT

One support element of the production platform on Scheuerle SPMT

Heavy lift and specialized transport service provider ALE moved a 4,140 tonne segment of a production platform for the Cygnus gas field in the North Sea.

The platform was moved on 168 axle lines of Scheuerle self propelled modular transporter (SPMT). Four support elements weighing between 1,180 and 2,125 tonnes were also transported.

The main operator for the Cygnus gas field is GDF Suez E&P UK. The completed gas field should account for five per cent of UK gas production, supplying 1.5 million households with energy, a spokesperson said.

On arrival at the quayside, the components were loaded onto a waiting barge and then transported to their final destination in the southern North Sea.

The gas field is due for completion by 2016.

Compaction is becoming smarter – and that’s changing how we build better roads
Caterpillar’s Rolf af Klinteberg on how new mapping tech can help improve consistency, reduce risk and lead to better decisions
KHL webinar to explore the changing industrial power landscape
Industry experts to discuss how businesses can build greater resilience as pressure on power infrastructure intensifies
Modapower targets the North American power gap
An object lesson in adapting gensets to local rules, applications and lead-time pressures – key factors in a successful market entry