Sarens performs critical installation at nuclear site

Premium Content

In spring 2022, the Tennessee Valley Authority (TVA) initiated a major nuclear refueling and maintenance outage so that four replacement steam generators could be installed at the Watts Bar nuclear plant – one of the USA’s newest commercial nuclear reactors.

The cranes included a Terex CC 8800, a Manitowoc 2250 for erecting and dismantling the CC 8800, and a Liebherr LR1400.

Sarens was called in to perform several major lifts for this high-security, high-stakes operation.

The team’s first mission was to remove two concrete dome sections at the Spring City, TN site. Sarens built two lift and support frames for the three-foot-thick concrete cutout, which was then water blasted for removal while the crew carefully monitored jack pressures and tensions. They used a Terex CC 8800 crane to remove two steel dome liner sections, four steam generator cubical roof sections and four old steam generators. These were lifted through cutouts atop the containment building, transitioned to a down/upending device and transported via SPMTs to a concrete storage facility.

Next, the Sarens team installed replacement dome liners, covers and four new steam generators, which were brought in from storage and upended so they could be sent through the roof of the containment structure. The new steam generators weighed approximately 800,000 pounds and measured over 68 feet long, with a nearly 16-foot diameter and 168-foot radius.

Could Istanbul be the construction industry’s next global meeting point?
Where continents, capital and contractors converge – Komatek 2026 could play a signficant role in turning Istanbul into a vital hub for the construction industry
Southwest Industrial Rigging gets new owner and leadership team
Entering a new era but aspiring to continue Harry Baker’s legacy
Trail King debuts automatic kingpin steering trailers
New trio hailed as a fundamental shift in heavy-haul equipment design