Technical lift by Prangl

By Laura Hatton29 April 2015

The dryer being hoisted in a tandem lift by a 500 tonne and a 700 tonne telescopic crane

The dryer being hoisted in a tandem lift by a 500 tonne and a 700 tonne telescopic crane

Lifting and specialist transport service provider Prangl, based in Austria, provided lifting services for the construction of a new nitric acid plant in Hungary.

The Pétfürdő plant, 100 km south west of Budapest, is made up of two ammonium nitrate production plants, with an additional plant for the fertiliser industry under construction.

For the construction of the third plant, Prangl was contracted to install a granulation system. The task involved lifting a 116 tonne dryer, a 61 tonne washing system, a 28 tonne chimney base and additional components into an existing 26 metre high steel structure.

All lifting operations were performed outside the plant using two cranes. The dryer was hoisted in horizontally in a tandem lift by 500 and 700 tonne capacity telescopic cranes.

To install the washer unit, 500 and 100 tonne capacity wheeled mobile cranes were used to open the tank and position the washer. The chimney base was installed using the 500 tonner.

Latest News
How did Saudi Aramco perform this major lift at Fadhili gas plant?
Early 2021 saw a critical lift performed at the Fadhili gas plant in Saudi Arabia when a reboiler tube was removed for inspection. Mustafa Al Abdulmohsin reports
Onshore construction completed for Triton Knoll
UK’s longest ever offshore wind cabling project concludes after three years
Sinoboom to give away scissor at ARA Show
Sinoboom North America will be giving away a Sinoboom 1330SE electric scissor lift in celebration of attending its first ARA Show