French nuclear project hit by more delays

Premium Content

10 October 2019

flamanville nuke

The Flamanville nuclear reactor

Electricite de France (EDF) says repair work on faulty welding at the Flamanville nuclear plant in northwest France will cost €1.5 billion.

The additional work will push the total cost of the project up by some 4%, to approximately €12.4 billion.

The repair work was demanded by the French nuclear watchdog ASN, following inspections; now EDF says its preferred approach to the repairs is to use robot welding.

The new welding, however, is unlikely to be ready for inspection by ASN before the end of 2020.

In a statement, EDF said, “The provisional schedule…results in the date of fuel loading at the end of 2022.” This would mean the reactor coming online some time in 2023 – four years later than initially anticipated.

EDF shares fell 1% following the news and are down more than 36% this year, adding to the company’s woes, which include delays and cost hikes on two similar reactors in the UK.

Engineering certainty: Lift planning’s expanding role in heavy industry
Driven by tighter critical lift procedures, heavier loads, and shrinking field experience, lift planning now sits at the center of construction execution
Istanbul – the world’s next meeting place
Levent Baykal, organiser of Komatek, the largest construction exhibition in Türkiye, talks to KHL’s Content Studio about his plans to put people at the heart of the show
The future of off-highway power is about integration, not just innovation
OEMs face growing complexity in powertrain decisions – but clarity is emerging around efficiency and uptime