Iraq's largest dam is at risk of an imminent collapse that could send a 20 m high wave of water into Mosul, a city of 1.7 million people, according to the latest assessment by the US Army Corps of Engineers.

The results of the assessment and the latest report by the Special Inspector General for Iraq Reconstruction (SIGIR) show that in May the US told Iraqi authorities to make Mosul Dam a national priority. SIGIR's report is also critical of a US$ 27 million reconstruction project designed to help shore up the dam, which has made almost no progress.

It also said US–funded “short–term solutions” had yet to significantly solve the dam's problems. SIGIR found failures in many of the contracts awarded to repair the dam. Among the failings were sub–standard construction and delivery of improper parts, as well as projects that were not completed despite full payments having been made.

The dam has been a problem for Iraqi engineers since it was completed in 1984. Built on water–soluble gypsum, which caused seepage within months of its completion, it was described “fundamentally flawed” by engineers at the time.

How smart technology is changing the crawler dozer workplace
Technology is helping dozer operators work more safely, accurately and consistently
Have your say: Help shape the State of Marketing 2027 report
Have your say: Help shape the State of Marketing 2027 report
WorkDry invests in pump fleet in preparation for extreme events
Company adds hundreds of new pumps in anticipation of extreme El Niño weather events.