Dam concerns

Premium Content

27 February 2008

Iraq's largest dam is at risk of an imminent collapse that could send a 20 m high wave of water into Mosul, a city of 1.7 million people, according to the latest assessment by the US Army Corps of Engineers.

The results of the assessment and the latest report by the Special Inspector General for Iraq Reconstruction (SIGIR) show that in May the US told Iraqi authorities to make Mosul Dam a national priority. SIGIR's report is also critical of a US$ 27 million reconstruction project designed to help shore up the dam, which has made almost no progress.

It also said US–funded “short–term solutions” had yet to significantly solve the dam's problems. SIGIR found failures in many of the contracts awarded to repair the dam. Among the failings were sub–standard construction and delivery of improper parts, as well as projects that were not completed despite full payments having been made.

The dam has been a problem for Iraqi engineers since it was completed in 1984. Built on water–soluble gypsum, which caused seepage within months of its completion, it was described “fundamentally flawed” by engineers at the time.

A Chinese OEM’s view of construction equipment today – and tomorrow
LiuGong’s Andrew Ryan believes forward-thinking OEMs must combine local execution, useful tech and a greater focus on total cost of ownership
Could Istanbul be the construction industry’s next global meeting point?
Where continents, capital and contractors converge – Komatek 2026 could play a signficant role in turning Istanbul into a vital hub for the construction industry
Southwest Industrial Rigging gets new owner and leadership team
Entering a new era but aspiring to continue Harry Baker’s legacy