Joint venture contractor Nass Murray and Roberts has installed the second of three turbine-carrying bridges at the 240 m high Bahrain World Trade Centre (BWTC).

The bridge will be one of three, 32 m long, 50 tonne, structures that will each be used to carry a 29 m diameter wind turbine. Once installed and working the turbines will provide about 15% of the two tower’ s electricity needs.

According to a project spokesman, the turbines are scheduled to be installed in January 2007.

The estimated cost of fabricating and erecting the building’ s bridges and turbines has been put at US$ 2.7 million.

Construction of the BWTC started in June 2004 and was expected to be complete by the summer of 2006.

Smart lifting: How to balance cost and safety
Rental experts discuss equipment strategies for today’s complex lifting challenges
How microgrids are powering the data center boom
As the global demand for data grows, businesses are looking beyond the grid for uninterrupted operation
Demolition & Recycling International October-December 2025
Demolition & Recycling International November-December 2025