December 2018: In June of 2018, Sarens was at the site of Engie Fabricom in Hoboken, Belgium, to weigh and load a topside module onto the Sarens barge “Paula”. The load weighed 4.200T, with a height of 35m, length of 75m, and width of 40m.

This particular topside module was actually a large transformer slated for installation in the middle of the Hohe See Offshore Wind Farm off Germany’s coast, where it would connect to the seashore as well as to all of the farm’s windmills.

Ten crew members were involved in weighing and loading the module at the quay. To execute the operation successfully, they used the following equipment:

  • 4 x 34 axle lines K24ST
  • 16 x weighing cell 500T
  • Sarens barge “Paula” 

One of the main challenges the crew faced was performing a roll-on operation onto a tidal river, which required careful contingency plans.

Sarens would like to recognise everyone who helped make this important operation a success.

Truckstop.com and ProMiles partner up to streamline heavy haul quoting
Truckstop.com and ProMiles have expanded the Heavy Haul Load Board with route-based quoting for oversize and overweight freight.
SCRA issues statement on tariff ruling by Supreme Court
Industry association comments on US ruling overturning import tariffs
Mi-Jack acquires new facility in Illinois, USA
New 200,000 square-foot production facility to meet critical capacity needs