Wyaralong Dam Project: Timeline

By Richard High12 May 2009

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralon

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralong Dam by Queensland Water Infrastructure (QWI). Courtesy: Queensland Water Infrastructure Pty Ltd

The following timeline is indicative only and is dependent on relevant approvals and weather conditions during construction.

Late 2008

Temporary construction water pipeline activities commence

Access Road preconstruction activities commence

Early 2009

Access Road construction commences

May 2009

Successful dam alliance announced

Successful contractor announced for Beaudesert to Boonah Road Realignment

Late 2009

Access Road complete

Major works on dam construction commence

By Mid 2010

Beaudesert - Boonah Road realignment construction complete

By Mid 2011

Project complete in advance of required date

Courtesy: Queensland Water Infrastructure Pty Ltd

Latest News
World Demolition Summit 2021 - conference update
Latest speakers and presentations as industry returns to an in-person event at Chicago in October
Strong second quarter figures from CNH
Company reports increases in order books
Sales for Caterpillar’s construction segment up 40%
Cat sees strong growth in second quarter of 2021 reflecting ‘continued improvement’ in markets