Wyaralong Dam Project: Timeline

Premium Content

12 May 2009

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralon

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralong Dam by Queensland Water Infrastructure (QWI). Courtesy: Queensland Water Infrastructure Pty Ltd

The following timeline is indicative only and is dependent on relevant approvals and weather conditions during construction.

Late 2008

Temporary construction water pipeline activities commence

Access Road preconstruction activities commence

Early 2009

Access Road construction commences

May 2009

Successful dam alliance announced

Successful contractor announced for Beaudesert to Boonah Road Realignment

Late 2009

Access Road complete

Major works on dam construction commence

By Mid 2010

Beaudesert - Boonah Road realignment construction complete

By Mid 2011

Project complete in advance of required date

Courtesy: Queensland Water Infrastructure Pty Ltd

Kabalen retires; Bray promoted at A1A Software
Bruce Kabalen calls it a day, Brittany Bray promoted
How rental businesses can modernise for growth
As margins tighten and expectations rise, rental firms embracing simple, data-led technology will be best placed to scale up and unlock new growth
Time to apply for an Engineeered Giving scholarship
30 June deadline for nonprofit foundation established by Engineered Rigging