Wyaralong Dam Project: Timeline

Premium Content

12 May 2009

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralon

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralong Dam by Queensland Water Infrastructure (QWI). Courtesy: Queensland Water Infrastructure Pty Ltd

The following timeline is indicative only and is dependent on relevant approvals and weather conditions during construction.

Late 2008

Temporary construction water pipeline activities commence

Access Road preconstruction activities commence

Early 2009

Access Road construction commences

May 2009

Successful dam alliance announced

Successful contractor announced for Beaudesert to Boonah Road Realignment

Late 2009

Access Road complete

Major works on dam construction commence

By Mid 2010

Beaudesert - Boonah Road realignment construction complete

By Mid 2011

Project complete in advance of required date

Courtesy: Queensland Water Infrastructure Pty Ltd

How smart technology is changing the crawler dozer workplace
Technology is helping dozer operators work more safely, accurately and consistently
Have your say: Help shape the State of Marketing 2027 report
Have your say: Help shape the State of Marketing 2027 report
2027 European Rental Awards open for entries
Includes new awards category for ‘People’ initiatives. Deadline for entries is 26 February 2027.