First base completed for Hinkley Point C

Premium Content

01 July 2019

HPC Concrete Pour

Reinforced with 5,000 tonnes of Welsh steel, the concrete base took 240 hours to complete

French-based energy provider EDF has announced that a key phase in the construction of the UK’s Hinkley Point C nuclear plant has been reached after completion of the base for the first reactor.

The company said after this achievement, work on the above-ground reactor 1 building can begin. It added that the second reactor would hit the same milestone in June next year.

Construction of the base was delivered on schedule by a joint venture between French contractor Bouygues and UK building firm Laing O’Rourke.

The final 9,000 m³ of concrete was the largest concrete pour in the UK, beating a record set by the Shard in London. Reinforced with 5,000 tonnes of steel sourced from Wales, the base has been under construction by the UK-French joint venture for six months.

The plant is expected to be completed by the end of 2025 and provide around 7% of Britain’s power needs or enough power for around 6 million homes. Once construction is finalised, the facility should have a power capacity of 3,200 MW.

What smarter cooling can do for the next generation of heavy equipment
Rethinking airflow, not simply adding capacity, is unlocking efficiency, uptime and better machine performance.
Meeting the data center power challenge… with batteries
Could battery energy storage systems (BESS) power the AI data center era?
Beyond uptime: The value of equipment support
Jessica Franck on how aftermarket support has evolved to become a strategic partnership