Hong Kong station by Leighton-Gammon

02 November 2015

Cranes on site include three 280 EC-H 16 Litronic units and fur luffing jib 355 HC-L Litronic 16/32

Cranes on site include three 280 EC-H 16 Litronic units and fur luffing jib 355 HC-L Litronic 16/32 models

Leighton-Gammon JV has put seven Liebherr tower cranes to work on the West Kowloon Terminus Station North in Hong Kong.

The cranes are working on the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL). Once complete, the rail link will have 15 platforms, connecting passageways, customs and immigration facilities, departure lounges, retail outlets and a large entrance hall. The WKT will connect to China and is expected to have almost 99,000 passengers daily.

To overcome issues with overcrowding, the terminus and railway line will be built underground. Five of the cranes were on site at the time o writing in early November, including three 280 EC-H 16 Litronic units, each with a capacity of 16 tonnes, and two luffing jib 355 HC-L Litronic 16/32 models. Two more 355 HC-L Litronic 16/32 models are due to be installed later this year.

The cranes are rented from Liebherr Singapore. William Tang, Liebherr Singapore sales manager, said, “These 280 EC-H units are performing a key role in crane duties to the underground levels, down to the lowest level at 33 m.

“The luffing jib cranes can handle a total lift capacity of 16 tonne, and 4.2 tonnes at the maximum 60 metre radius,” Tang added. “Most of the work for these units is on the superstructure and for subway and footbridge elements, much of which is prefabricated and consequently needs heavy lift cranes. Because of the enormous amount of lifting that is required at diverse parts of this project, luffing jibs are essential.”

Work at the site includes an open-cut excavation of approximately 1.7 million cubic metres of earth to a depth of 33 m and the use of 600,000 cubic metres of concrete and 150,000 tonnes of reinforcement steel, a spokesperson said. The roof will be made of 7,000 tonnes of steel trusses and supported by nine 30 m high columns. The roof is being constructed with prefabricated components, weighing up to 40 tonnes each and spanning up to 45 m.

Latest News
Platform Basket delivers first 54m spider
The innovative 54T spider goes to Minoege
Andy Wright joins UK power specialist
Former Sunbelt UK CEO appointed executive chair
Stantec acquires UK-based engineering design rival Hydrock
Canadian engineering firm Stantec has bought its UK-based engineering design rival Hydrock, in a move that it said would strengthen its UK offering.