Milestone for ALE on Serbian bridge

13 September 2017

Image 1

Azvi contracted ALE for the bridge installation

International heavy lift and transport specialist ALE has launched the first section of the Zezelj bridge, weighing 4,750 tonnes, in Novi Sad, Serbia.

Spain-based specialist infrastructure contractor Azvi contracted ALE for the project which started in June 2017. In addition to launching two arches and two span sections, ALE also did the jacking and weighing. Equipment used included, jacks, load cells, hydraulic winches and pontoons, plus a skidding system, ballast system and a purpose-built gantry.

The first section was raised using jacks with a total capacity of 7,600 tonnes.

In anticipation of the water level changing in the river, measures were taken to maintain schedules and minimise cost variation. This included adapting the height of the gantry to accommodate different water levels and using a modular steel structure with the combination of hydraulic jacks on top of the main columns, ALE explained.

Francisco Gómez, ALE project engineer, said, “We have a team of bridge experts working on this and, by finding a solution that will allow the client to install the bridge with a range of 4 metres between the water levels, we are reducing the project costs and optimising the overall duration of the project so the remaining building work of the railway infrastructure can continue.

“By providing beneficial solutions such as these, we can showcase our capabilities in the sector. Now we have completed the engineering phase, the first jacking operation, and launching operations of the first bridge section, we can continue to progress to the next stage of this complex project,” Gómez continued.

Image 2

The 4,750 tonne arch section in place

Latest News
Huisman to build another 2,600 tonne crane
Second 2,600 tonne capacity offshore wind turbine installation vessel crane for Eneti via DSME
New CEO at project transport specialist Silvasti
Lauri Riipinen takes CEO role as Ville Silvasti moves to be chairman of the board
JLG introduces Quad Tracks
The Quad Tracks are initially available on new 600S and 600SJ boom lifts, as well as some 2-wheel steer models