Milestone for ALE on Serbian bridge

Premium Content

13 September 2017

Image 1

Azvi contracted ALE for the bridge installation

International heavy lift and transport specialist ALE has launched the first section of the Zezelj bridge, weighing 4,750 tonnes, in Novi Sad, Serbia.

Spain-based specialist infrastructure contractor Azvi contracted ALE for the project which started in June 2017. In addition to launching two arches and two span sections, ALE also did the jacking and weighing. Equipment used included, jacks, load cells, hydraulic winches and pontoons, plus a skidding system, ballast system and a purpose-built gantry.

The first section was raised using jacks with a total capacity of 7,600 tonnes.

In anticipation of the water level changing in the river, measures were taken to maintain schedules and minimise cost variation. This included adapting the height of the gantry to accommodate different water levels and using a modular steel structure with the combination of hydraulic jacks on top of the main columns, ALE explained.

Francisco Gómez, ALE project engineer, said, “We have a team of bridge experts working on this and, by finding a solution that will allow the client to install the bridge with a range of 4 metres between the water levels, we are reducing the project costs and optimising the overall duration of the project so the remaining building work of the railway infrastructure can continue.

“By providing beneficial solutions such as these, we can showcase our capabilities in the sector. Now we have completed the engineering phase, the first jacking operation, and launching operations of the first bridge section, we can continue to progress to the next stage of this complex project,” Gómez continued.

Image 2

The 4,750 tonne arch section in place

Smarter by design: How intelligent excavators are delivering better jobsite results
Integrated technology is helping contractors improve accuracy, productivity and control without neglecting the fundamentals of machine performance
Choosing the right AWP for a constrained jobsite
A look at how site restrictions and task requirements inform aerial platform selection
The right tire for the right application
When the demands of a jobsite dictate tire selection, field knowledge and data are key to optimising fleet performance