Power plant uses Peri Up

Premium Content

04 November 2013

The Peri Up system was used for the power plant construction in Eemshaven

The Peri Up system was used for the power plant construction in Eemshaven

Peri has installed its Peri Up Rosett Flex system for the construction of the Eemshaven power plant in the Netherlands.

The platforms were erected on two electric filters for flue gas desulphurisation, measuring 64 m long and 35 m high, to provide a safe position for workers carrying out welding and insulation work.

The 1600 MW Eemshaven power plant in the Dutch province of Groningen is scheduled to open in 2014, following a four-year build programme.

The modular scaffolding system can be assembled with the guardrail in advance, guaranteeing a high degree of safety from the start.

An externally fitted working scaffold with integrated 75 cm flights of stairs was also used for the final assembly of eight inlet ducts. The scaffold solution can be adjusted through its metric grid arrangement to suit the up to 4.5 m cantilevered funnel shape – in part, suspended from a gallows structure comprised of Peri Up system components.

Putting the seal on innovative filtration
When you’re working with machinery, uptime is money – so why allow downtime on a jobsite to be triggered by something as unglamorous as an air filter?
Smart lifting: How to balance cost and safety
Rental experts discuss equipment strategies for today’s complex lifting challenges
How microgrids are powering the data center boom
As the global demand for data grows, businesses are looking beyond the grid for uninterrupted operation