Vietnam monorail for ALE

16 December 2014

ALE is using 17 axle lines of conventional trailers, two prime movers and two 200 tonne capacity bol

ALE is using 17 axle lines of conventional trailers, two prime movers and two 200 tonne capacity bolsters to transport the girders

At the beginning of December ALE was halfway through a project to transport bridge girder sections for a monorail system construction programme in Vietnam.

In total, 254 bridge girders will be moved on the project. The girders weigh 230 tonnes each and are 32 metres long. They will be transported 13 km from a casting yard in Duong Noi to the site of the Cat Linh - Ha Dong line.

ALE is using 17 axle lines of conventional trailers, two prime movers and two 200 tonne capacity bolsters to transport the girders.

Van Duc Trung, ALE operations manager, said, “We are really proud to have such an instrumental role in this landmark project for the country. So far, we have moved over 40 % of the girders and we are on track to complete on schedule.

“We have carefully selected the most suitable equipment and configurations for the transportation. As the girders are 32 metres long, we have utilised two bolsters for support. The team are working hard and we are continuing to progress with this milestone project.”

The monorail project will be completed by the end of 2015.

Latest News
EquipmentShare mulls US IPO in 2025
Construction equipment rental company equipment share could go public as early as next year (2025), according to a report by Bloomberg.
New Teupen spider for multiple markets
Product aimes at US market follows Teupen’s acquisition by Altec
Dragon crushers continuing to gain in popularity
Company owner and director presents the CR400 model to Intermat crowds