Mammoet uses LR 13000 on Aeolus

Premium Content

28 April 2014

Mammoet’s LR 13000 installs platform leg on Aeolus

Mammoet’s LR 13000 installs platform leg on Aeolus

International heavy lift and transport provider Mammoet used its 3,000 tonne capacity Liebherr LR 13000 to help install four platform legs on Van Oord’s new wind turbine installation vessel, the Aeolus.

The platform legs measure 87 metres long and weigh 920 tonnes each. To carry out the task, Mammoet used specially designed top lifting tools and a tailing frame. Mammoet will also be involved in installing four spud cans, a company spokesperson said.

The project started on 22 April. The Aeolus is scheduled to be operational in July.

Webinar: Caterpillar experts to discuss the increasing importance of temporary power
Live event on July 7, will explore how businesses are using temporary power solutions to strengthen energy resilience
Product launch update: new tower cranes
New tower cranes launched into the North American market this year
Why rugged electronics are becoming mission-critical for off-road OEMs
Connectivity and digital controls are reshaping heavy equipment and manufacturers are finding performance depends as much on durable electronics as on the vehicles themselves