Mammoet’s LR 13000 installs platform leg on Aeolus

Mammoet’s LR 13000 installs platform leg on Aeolus

International heavy lift and transport provider Mammoet used its 3,000 tonne capacity Liebherr LR 13000 to help install four platform legs on Van Oord’s new wind turbine installation vessel, the Aeolus.

The platform legs measure 87 metres long and weigh 920 tonnes each. To carry out the task, Mammoet used specially designed top lifting tools and a tailing frame. Mammoet will also be involved in installing four spud cans, a company spokesperson said.

The project started on 22 April. The Aeolus is scheduled to be operational in July.

How Donaldson is putting the seal on innovative filtration
When you’re working with machinery, uptime is money – so why allow downtime on a jobsite to be triggered by something as unglamorous as an air filter?
Smart lifting: How to balance cost and safety
Rental experts discuss equipment strategies for today’s complex lifting challenges
How microgrids are powering the data center boom
As the global demand for data grows, businesses are looking beyond the grid for uninterrupted operation