Mammoet uses LR 13000 on Aeolus

Premium Content

28 April 2014

Mammoet’s LR 13000 installs platform leg on Aeolus

Mammoet’s LR 13000 installs platform leg on Aeolus

International heavy lift and transport provider Mammoet used its 3,000 tonne capacity Liebherr LR 13000 to help install four platform legs on Van Oord’s new wind turbine installation vessel, the Aeolus.

The platform legs measure 87 metres long and weigh 920 tonnes each. To carry out the task, Mammoet used specially designed top lifting tools and a tailing frame. Mammoet will also be involved in installing four spud cans, a company spokesperson said.

The project started on 22 April. The Aeolus is scheduled to be operational in July.

How smart equipment is improving jobsite productivity
In the face of rising costs, tighter margins and labor shortages, there has never been a greater need to make the best use of every hour on site
What smarter cooling can do for the next generation of heavy equipment
Rethinking airflow, not simply adding capacity, is unlocking efficiency, uptime and better machine performance.
Meeting the data center power challenge… with batteries
Could battery energy storage systems (BESS) power the AI data center era?