Vietnam monorail for ALE

Premium Content

16 December 2014

ALE is using 17 axle lines of conventional trailers, two prime movers and two 200 tonne capacity bol

ALE is using 17 axle lines of conventional trailers, two prime movers and two 200 tonne capacity bolsters to transport the girders

At the beginning of December ALE was halfway through a project to transport bridge girder sections for a monorail system construction programme in Vietnam.

In total, 254 bridge girders will be moved on the project. The girders weigh 230 tonnes each and are 32 metres long. They will be transported 13 km from a casting yard in Duong Noi to the site of the Cat Linh - Ha Dong line.

ALE is using 17 axle lines of conventional trailers, two prime movers and two 200 tonne capacity bolsters to transport the girders.

Van Duc Trung, ALE operations manager, said, “We are really proud to have such an instrumental role in this landmark project for the country. So far, we have moved over 40 % of the girders and we are on track to complete on schedule.

“We have carefully selected the most suitable equipment and configurations for the transportation. As the girders are 32 metres long, we have utilised two bolsters for support. The team are working hard and we are continuing to progress with this milestone project.”

The monorail project will be completed by the end of 2015.

Will fuel-agnostic engines power the next era of construction?
Flexible engine platforms are emerging as a way to balance performance, flexibility and future regulatory demands
Beyond torque: The challenge of power management for crushing equipment
How OEMs and operators are managing to maximise uptime for equipment that has to pass the ultimate stress test on a daily basis
Crawler-mounted boom lifts rise to the challenge of bridge work
From remote creek beds to inner city overpasses, crawler-mounted boom lifts are proving indispensable for bridge construction, inspection and maintenance