The cargo was moved along the 2,200 km route through the Mangystau desert using 34 axle lines of con

The cargo was moved along the 2,200 km route through the Mangystau desert using 34 axle lines of conventional trailers

Heavy lift and specialized transport company ALE completed the second stage of a transport project across the Mangystau desert in Kazakhstan.

The project consisted of transporting a 140 tonne steam turbine and 180 tonne generator from Ersai in Kazakhstan to the Tashkent Thermal Power Plant in Uzbekistan.

The cargo was moved along the 2,200 km route through the Mangystau desert using 34 axle lines of conventional trailers with three heavy duty prime movers.

Ali Yoldashov, ALE regional operations manager, said, “ALE was awarded the contract for the second stage after the client was impressed with the project management of the complex and challenging route and the professionalism shown during the first stage last year. The high equipment utilisation of ALE’s on-site facilities resulted in minimal standby time and a timely delivery.”

It took one month to transport the steam turbine and generator to the Tashkent Thermal Power Plant.

The changing role of power units in off-highway equipment
Isuzu describes how pre-validated systems can lighten the engineering load for OEMs
How installation determines alignment success in rotating machinery
Roman Megela explains the impact of installation quality on machine reliability, energy-efficiency and sustainability
Building the intelligent mine: Why integration will define mining’s next era
Yu Xiao Ying, Head of Smart Mining Projects at Zoomlion on how and why mining is entering a period of profound transformation