Mammoet completes petrochemical job

Premium Content

Heavy lift and transportation specialist Mammoet completed the demolition and replacement of five heater furnaces in what it described as a “congested” 86-year-old petrochemical plant in Texas City, Texas, USA.

DJI_0003

According to Mammoet, the dimensional constraints in the refinery made crane construction challenging as there was no space to lay down the booms and jibs to assemble the two CC 8800 lattice boom crawler cranes it needed to use for the job.

DJI_0057

Mammoet’s solution was to assemble the two CC 8800s in the air, using two other cranes to lift the jibs and booms. This, Mammoet said, enabled it to salvage and install larger sections of the furnaces, cutting the project’s duration by more than a month.

Once assembled the two CC 8800s were on the site for several months and carried out more than 50 critical lifts.

 

How less can be more: Rethinking cooling system design for modern heavy equipment
Smarter airflow, not bigger systems, is aiding engine efficiency and uptime
Kabalen retires; Bray promoted at A1A Software
Bruce Kabalen calls it a day, Brittany Bray promoted
How rental businesses can modernise for growth
As margins tighten and expectations rise, rental firms embracing simple, data-led technology will be best placed to scale up and unlock new growth