Heavy lift and transportation specialist Mammoet completed the demolition and replacement of five heater furnaces in what it described as a “congested” 86-year-old petrochemical plant in Texas City, Texas, USA.

DJI_0003

According to Mammoet, the dimensional constraints in the refinery made crane construction challenging as there was no space to lay down the booms and jibs to assemble the two CC 8800 lattice boom crawler cranes it needed to use for the job.

DJI_0057

Mammoet’s solution was to assemble the two CC 8800s in the air, using two other cranes to lift the jibs and booms. This, Mammoet said, enabled it to salvage and install larger sections of the furnaces, cutting the project’s duration by more than a month.

Once assembled the two CC 8800s were on the site for several months and carried out more than 50 critical lifts.

 

NCCCO Foundation launches Crane Career Advisor program
New resource offering guidance to people interested in working in the crane sector
Engineering certainty: Lift planning’s expanding role in heavy industry
Driven by tighter critical lift procedures, heavier loads, and shrinking field experience, lift planning now sits at the center of construction execution
Istanbul – the world’s next meeting place
Levent Baykal, organiser of Komatek, the largest construction exhibition in Türkiye, talks to KHL’s Content Studio about his plans to put people at the heart of the show