CC3800-1 performs its first lift in Australia

Premium Content

12 October 2020

124107_20200818_091039

NRW contracting commissioned Sarens to perform the crucial lift of rail bridge girders over operating railway track for Fortescue Metals Group’s Eliwana Project in the Pilbara, Western Australia. The entire operation of transporting two girders from the laydown area to the lifting location and installation had to be completed during the rail shut down window of an 8 hours access window.

The crane was imported and mobilised to the site in 3 weeks and assembled in 5 days. The other equipment used during the project were: 

  • LTM 1150
  • Two 6-Axle Line SPMT 
  • Two PPU

Two girders weighing up to 155T, were transported from the laydown area to the lifting position and lifted at a radius of up to 42m. The entire operation was safely completed by a crew of 8 members. According to Project Manager, Minhaj Rizvi, “The rail shutdown window of 8 hours was a challenge. Our team worked with meticulous planning and preparation and executed the lifts safely and efficiently within shutdown window with zero incidents.”

Parked in plane sight: Why GSE fleets rely on large spark-ignited engines
Examining how proven technology can help airport fleets balance uptime, cost, flexibility and lower emissions
Accessing aging infrastructure: Choosing the right AWP for the application
How site conditions determine which aerial work platform is best suited to the project
The evolution of construction site safety: Why smart machines matter
Intelligent intervention that can help contractors prevent incidents without compromising productivity