ALE loads out more than 20,000 tonnes

Premium Content

05 March 2018

Image 2

Each module weighed around 10,000 tonnes

International specialist contractor ALE loaded-out two modules with a combined weight of more than 20,000 tonnes for the Martin Linge platform project in South Korea.

They were the utility and process modules and ALE-Offshore Services performed both the weighing and load-out operations. The utility module was 9,580 tonnes and the process module weighed 10,850 tonnes. After weighing on a synchronised system the modules were loaded out onto the same vessel in separate skidding operations over two months. 

Commenting on the job, Edwin Blosser, ALE project engineer, said, “In consideration of the sheer size and scale of the piece, to perform the load-out was no mean feat. As the modules had a high centre of gravity, it was extremely challenging to load them out onto the same vessel and control the vessel’s stability. We utilised a computerised skidding system to overcome this, as well as quay jacks to monitor the load.”


 

First expert speaker announced for power transition webinar
Moog Construction’s Dr Nate Keller to join panel for February 17 event
Is total cost of ownership now the real measure of equipment value?
As sustainability pressures, technology and rising operating costs reshape construction economics, contractors are looking beyond purchase price to understand what machines truly cost over their lifetime
How Donaldson is putting the seal on innovative filtration
When you’re working with machinery, uptime is money – so why allow downtime on a jobsite to be triggered by something as unglamorous as an air filter?