Olympic underpass pushed through

Premium Content

06 January 2010

Skanska employed a jacked box solution with hydraullic rams to push through the underpass into the O

Skanska employed a jacked box solution with hydraullic rams to push through the underpass into the Olympic Park.

A new link to London's Olympic Park has been completed on schedule in just 28 days using a pre-constructed concrete box section, tunnelling techniques and hydraulic rams.

Contractor Skanska employed a ‘jacked box' method to push through the underpass to the Olympic Park without affecting traffic flow on the six lane carriageway of the A12 above.

The concrete box forming the underpass was constructed in three sections and measures 50 m in length. With a height of 8m and a width of 11,5 m the complete unit weighed 3500 tonnes. Tunnelling techniques were used to excavate the ground ahead of the box while a series of hydraulic rams then pushed the box into the excavated tunnel face.

Olympic Delivery Authority chairman John Armitt said, "The delivery of this critical engineering project on time is a significant achievement given the complexities and challenges involved. It is a testament to the hard work and ingenuity of our workers and engineers working round the clock to construct the new underpass beneath a busy dual carriageway, without causing any disruption to motorists."

Smart lifting: How to balance cost and safety
Rental experts discuss equipment strategies for today’s complex lifting challenges
How microgrids are powering the data center boom
As the global demand for data grows, businesses are looking beyond the grid for uninterrupted operation
Demolition & Recycling International October-December 2025
Demolition & Recycling International November-December 2025