Barge transport for major Asian fuel project

Premium Content

Total Movements was involved in a challenging transport which included moving 700 freight-tonnes of equipment in loads more than 7 metres high.

The cargo was more than 7 metres high

The cargo was transported from the supplier’s plant to a load port on the West coast of India.

A spokesperson for Total Movements said, “Shifting of these oversized pieces within the plant, road transportation from the supplier’s plant to the nearest jetty, barging to the nearest major seaport, and feeding alongside the vessel were all part of our scope.

“The cargo’s COG (centre of gravity) was higher than usual, which posed a significant challenge.

“The nominated loading jetty was a tidal jetty, which necessitated special pilotage and mooring arrangements.

“Our engineering and operational team made site visits, had detailed discussions with multiple stakeholders, technical simulations, to execute this movement.”

Check back soon for more detail on this transport project as it becomes available.

The cargo’s COG (centre of gravity) was higher than usual, posing a significant challenge
Technical simulations helped plan the transportation
The right tire for the right application
When the demands of a jobsite dictate tire selection, field knowledge and data are key to optimising fleet performance
Why material recovery is becoming a competitive advantage for demolition contractors
As construction and demolition waste recovery demands increase, so does the need to make the process more efficient
Engineering demolition in a live industrial environment: The Matosinhos Refinery
When established methods are not enough, safety has to drive the solution