Mega load out for ALE

Premium Content

15 September 2014

The modules weighed between 31 and 1,925 tonnes each

The modules weighed between 31 and 1,925 tonnes each

Heavy lift and transport specialist ALE has completed the load out of 111 modules at a fabrication yard in Bauan Batangas, Philippines.

The project was undertaken by the Philippines branch of ALE. The modules weighed between 31 and 1,925 tonnes each. A number of vessels and other equipment were also transported.

One of the modules was moved using a skidding system. The vessel weighed 135 tonnes and was skidded at 5 metres high using a push and pull system, hydraulic jacks and hijack frame, a spokesperson said. Some of the heaviest modules, weighing 1,925 and 966 tonnes, were loaded out using 104 axles of Nicolas self propelled modular transporter (SPMT).

Noli Cainto, ALE Philippines head of operations, said, “I want to congratulate the team on their successful completion of the project. We are proud of the hard work put in by all of the team involved and it demonstrates the consistency of providing resolutions so that the project is completed whilst avoiding any delays."

The future of off-highway power is about integration, not just innovation
OEMs face growing complexity in powertrain decisions – but clarity is emerging around efficiency and uptime
A Chinese OEM’s view of construction equipment today – and tomorrow
LiuGong’s Andrew Ryan believes forward-thinking OEMs must combine local execution, useful tech and a greater focus on total cost of ownership
Could Istanbul be the construction industry’s next global meeting point?
Where continents, capital and contractors converge – Komatek 2026 could play a signficant role in turning Istanbul into a vital hub for the construction industry