Sensitive bridge work in Brazil

Premium Content

03 June 2013

Surgical and controlled demolition was required from Complex Ltda during the demolition of a bridge

Surgical and controlled demolition was required from Complex Ltda during the demolition of a bridge in Vitoria, Brazil

Brazilian contractor Complex Ltda was faced with a challenge when it won the contract to demolish an old bridge that connected districts in the city of Vitoria in the state of Espirito Santo. The old bridge could no longer cope with the increasing volume of traffic crossing between the city districts and it had in fact been replaced by three new structures. Its demolition required the removal of 1,300 cubic metres of concrete, with a provision of the contract requiring that for environmental reasons none of the resulting demolition debris was to be allowed to fall into the river below.

Complex first used an Atlas Copco SB 452 breaker to remove the lighter concrete structures such as the parapet and concrete surfacing. Once this had been done, two Atlas Copco MB 1700 breakers and two CC1700 CombiCutters, mounted on Volvo EC210 and Cat 416E carriers, were then used to first remove the concrete bridge deck and then the 10 concrete beams that made up the bridge’s main structure. All resulting debris was received by a barge moored in the river below the bridge and was then transported to a recycling plant for further processing.

Truckstop.com and ProMiles partner up to streamline heavy haul quoting
Truckstop.com and ProMiles have expanded the Heavy Haul Load Board with route-based quoting for oversize and overweight freight.
SCRA issues statement on tariff ruling by Supreme Court
Industry association comments on US ruling overturning import tariffs
Mi-Jack acquires new facility in Illinois, USA
New 200,000 square-foot production facility to meet critical capacity needs