Sinkhole protection

Premium Content

01 May 2008

Main contractor walter-heilit has used huesker's fortec geosynthetic reinforcement system for road repairs as part of Verkehrsprojekte Deutsche Einheit (VDE) road project No. 13, which includes construction of the A143 Western Relief Road at Halle, and interchanges on the A7 at Göttingen and the A14 at Leipzig, as well as the western by-pass around Halle between the A38 and A14 motorways.

As it approaches the residential suburb of Halle Neustadt, the route crosses an area of former brown coalmine workings, prone to the formation of sinkholes. Protection against this subsidence was provided by a bridging system using a single layer of high-strength geosynthetic reinforcement comprising Huesker's Fortrac-AM (aramid/PVA).

The geogrid was placed in one layer longitudinally with the transfer of tensile force being assured by transverse overlaps, tensioned during installation, by a specially designed ‘laying device'.

A gravel and sand layer was then spread over the reinforcement, this pushed the material forward over the tensioned geogrid and held it in place.

This was followed by further compaction. In total about 160000 m2 of geogrid was supplied, sufficient to protect over 2,6 km of the A143 Western Relief Road.

Kabalen retires; Bray promoted at A1A Software
Bruce Kabalen calls it a day, Brittany Bray promoted
How rental businesses can modernise for growth
As margins tighten and expectations rise, rental firms embracing simple, data-led technology will be best placed to scale up and unlock new growth
Time to apply for an Engineeered Giving scholarship
30 June deadline for nonprofit foundation established by Engineered Rigging