Sinkhole protection

Premium Content

01 May 2008

Main contractor walter-heilit has used huesker's fortec geosynthetic reinforcement system for road repairs as part of Verkehrsprojekte Deutsche Einheit (VDE) road project No. 13, which includes construction of the A143 Western Relief Road at Halle, and interchanges on the A7 at Göttingen and the A14 at Leipzig, as well as the western by-pass around Halle between the A38 and A14 motorways.

As it approaches the residential suburb of Halle Neustadt, the route crosses an area of former brown coalmine workings, prone to the formation of sinkholes. Protection against this subsidence was provided by a bridging system using a single layer of high-strength geosynthetic reinforcement comprising Huesker's Fortrac-AM (aramid/PVA).

The geogrid was placed in one layer longitudinally with the transfer of tensile force being assured by transverse overlaps, tensioned during installation, by a specially designed ‘laying device'.

A gravel and sand layer was then spread over the reinforcement, this pushed the material forward over the tensioned geogrid and held it in place.

This was followed by further compaction. In total about 160000 m2 of geogrid was supplied, sufficient to protect over 2,6 km of the A143 Western Relief Road.

The right tire for the right application
When the demands of a jobsite dictate tire selection, field knowledge and data are key to optimising fleet performance
Why material recovery is becoming a competitive advantage for demolition contractors
As construction and demolition waste recovery demands increase, so does the need to make the process more efficient
Engineering demolition in a live industrial environment: The Matosinhos Refinery
When established methods are not enough, safety has to drive the solution